Fixing errors at North Shore sewage plant to cost Metro Vancouver another $85 million

ARTICLE AD BOX

The approved budget for the beleaguered wastewater project remains $1.058 billion, but that could increase as Metro Vancouver works to determine an updated cost estimate and schedule.

Metro Vancouver hired PCL Constructors Westcoast Inc. on a contract worth $40 million to develop a new plan for the troubled North Vancouver wastewater treatment plant, including a revised budget and schedule. Concrete deficiencies and other issues have led to a request for an additional $85 million. Metro Vancouver hired PCL Constructors Westcoast Inc. on a contract worth $40 million to develop a new plan for the troubled North Vancouver wastewater treatment plant, including a revised budget and schedule. Concrete deficiencies and other issues have led to a request for an additional $85 million. Photo by Francis Georgian /PNG

Previous errors and repairs could triple the cost of “early works construction” to $85 million on Metro Vancouver’s delayed and over-budget North Shore wastewater treatment plant.

Advertisement 2

Vancouver Sun NewsConnect Powered by Postmedia Network

THIS CONTENT IS RESERVED FOR SUBSCRIBERS ONLY

Subscribe now to read the latest news in your city and across Canada.

  • Unlimited online access to articles from across Canada with one account
  • Get exclusive access to the Vancouver Sun ePaper, an electronic replica of the print edition that you can share, download and comment on
  • Enjoy insights and behind-the-scenes analysis from our award-winning journalists
  • Support local journalists and the next generation of journalists
  • Daily puzzles including the New York Times Crossword

SUBSCRIBE TO UNLOCK MORE ARTICLES

Subscribe now to read the latest news in your city and across Canada.

  • Unlimited online access to articles from across Canada with one account
  • Get exclusive access to the Vancouver Sun ePaper, an electronic replica of the print edition that you can share, download and comment on
  • Enjoy insights and behind-the-scenes analysis from our award-winning journalists
  • Support local journalists and the next generation of journalists
  • Daily puzzles including the New York Times Crossword

REGISTER TO UNLOCK MORE ARTICLES

Create an account or sign in to continue with your reading experience.

  • Access articles from across Canada with one account
  • Share your thoughts and join the conversation in the comments
  • Enjoy additional articles per month
  • Get email updates from your favourite authors

The request for more funds is expected to come before Metro’s liquid waste committee next week.

Sunrise presented by Vancouver Sun

Start your day with a roundup of B.C.-focused news and opinion delivered straight to your inbox at 7 a.m., Monday to Friday.

By clicking on the sign up button you consent to receive the above newsletter from Postmedia Network Inc. You may unsubscribe any time by clicking on the unsubscribe link at the bottom of our emails or any newsletter. Postmedia Network Inc. | 365 Bloor Street East, Toronto, Ontario, M4W 3L4 | 416-383-2300

Early last year, Metro hired PCL Constructors Westcoast Inc. on a contract worth $40 million to develop a new plan for the troubled project, including a revised budget and schedule. The move came after the regional district terminated its contract with the treatment plant’s initial contractor, Acciona Wastewater Solutions LP, after it missed key milestones and appeared to have “abandoned” the project.

Acciona Wastewater, a subsidiary of a Spanish multinational, was hired in 2017 on a design-build-finance basis to complete what was to be a $700 million replacement for the Lions Gate wastewater plant. The project ended up being 2½ years overschedule and costs ballooned to $1.058 billion.

Article content

Article content

According to a report by Cheryl Nelms, Metro’s general manager for project delivery, PCL and design consultant AECOM have “identified significant deficiencies in (the previous) design and construction, and, in some cases, more extensive deficiencies than originally anticipated.”

Work over the last several months has been focused on identifying and repairing “concrete deficiencies” on structures built by Acciona. The project needs more repairs, and more challenging repair work, than originally expected. The design is also not as far along as reported by Acciona, according to the report.

As a result, the planning phase will take longer — and cost more.

A worker at the site of Metro Vancouver’s new wastewater treatment plan on March 10. A worker at the site of Metro Vancouver’s new wastewater treatment plan on March 10. Photo by Francis Georgian /PNG
A file photograph of construction on the sewage plant. A file photograph of construction on the sewage plant. Photo by Francis Georgian /PNG

The liquid waste committee will discuss the request at its March 15 meeting. If accepted, it will go to the Metro board for a decision at the end of the month.

Article content

Despite the request for an additional $85 million, the approved budget for the wastewater project remains $1.058 billion, including construction, which would be done as part of the project’s second phase.

“The current approved project budget and current year cash flow can accommodate the requested change order to the PCL contract,” says the report.

But there’s no guarantee the budget won’t increase eventually.

In a statement sent to Postmedia News, Nelms said the construction issues need to be addressed to “inform development of an accurate cost estimate and schedule, and allow construction to progress.”

A plan to complete the project, including an updated cost estimate and schedule, is expected to go before the Metro board in mid-2023. The main construction contract for the project’s second phase will also be awarded later this year.

Article content

In an update to the Metro liquid waste committee, Peter Navratil, GM of liquid waste services, says PCL has been correcting problems in the existing concrete structures and pouring concrete for walls and foundations for the influent pumping station and power building, while preparing for future concrete pours for the operations and management building.

Design work is also continuing, as well as equipment procurement and engagement with Metro’s operations and maintenance teams to review the design, and the development of contracts for technical services and construction completion.

A file photo of the plant during early construction. A file photo of the plant during early construction. Photo by Francis Georgian /PNG

Nelms couldn’t comment on a continuing lawsuit over the sewage plant debacle. Metro is countersuing Acciona, arguing the company’s breaches will cost the regional district $500 million, according to court documents filed in B.C. Supreme Court in Vancouver last summer.

Article content

Acciona originally sued Metro for $250 million, saying it was wrongfully terminated from the project and blamed delays and cost overruns on problems that included Metro picking an inadequate site for the facility and the regional district’s “wrongful conduct” during the design and review process.

Metro, in its response, disputed those claims and countered that Acciona failed to perform its obligations under the project agreement due to its “inability to, and failure to, properly interpret” design specifications, submitting design elements with numerous errors, while showing a lack of understanding of applicable laws, including B.C.’s Building Code.

— With files from Derrick Penner

  1.  Francis Georgian / Postmedia) , Vancouver. Vancouver Reporter: ,  ( Francis Georgian   /  PNG staff photographer) [PNG Merlin Archive]

    Metro Vancouver to hire new contractor for troubled $1-billion North Shore treatment plant

  2. Construction site for the North Shore Wastewater Treatment Plant in North Vancouver, where the project contractor appeared to have stopped work.

    Metro Vancouver terminates contract of billion-dollar 'abandoned' North Shore wastewater treatment plant

  3. Spanish construction giant Acciona and Metro Vancouver are suing each other over the stalled construction of the new North Shore sewage plant.

    Metro Vancouver files $500 million countersuit over North Shore sewage plant debacle

gluymes@postmedia.com

twitter.com/glendaluymes


Support our journalism: Our in-depth journalism is possible thanks to the support of our subscribers. For just $3.50 per week, you can get unlimited, ad-lite access to The Vancouver Sun, The Province, National Post and 13 other Canadian news sites. Support us by subscribing today: The Vancouver Sun | The Province.